Microsoft exits UK's largest AI data centre over power grid delays to 2030s
Microsoft has pulled out of Nscale's Loughton, Essex AI data centre project after being informed that adequate grid power supply will not be available until the early to mid-2030s. The withdrawal is a significant setback for Nscale, which was planning a Wall Street IPO at a $35 billion valuation, and highlights infrastructure challenges facing the UK's sovereign AI strategy.
Quick Facts
- Microsoft withdrew from partnership with Nscale on AI data centre project
- UK Power Networks informed Nscale of power supply delays
- Nscale clearing scaffolding yard site
- Nscale exploring alternative power sources
- Nscale pursuing Wall Street IPO




Microsoft has withdrawn from its partnership with Nscale on the Loughton, Essex AI data centre project, citing concerns about power supply infrastructure. The facility, announced in 2025 as the UK's largest sovereign AI data centre and heralded by the government as a cornerstone of the country's AI strategy, was originally planned to open in 2026. However, UK Power Networks informed Nscale in October that the site would not receive sufficient grid power until the early to mid-2030s, forcing a significant operational delay.
Microsoft was positioned as Nscale's anchor tenant and had pledged to fund a supercomputer at the site as part of a £2 billion commitment announced last year. The company's exit represents a material blow to Nscale ahead of its planned initial public offering, for which the company is targeting a $35 billion valuation on Wall Street and seeking to raise up to $30 billion. IPO filings revealed that approximately 85% of Nscale's contracted business depends on Microsoft and AI company Anthropic. Microsoft confirmed it remains engaged with Nscale on separate projects in Norway, Portugal, and the United States.
Nscale stated it remains committed to the Loughton project and the UK market, and is exploring alternative power sources for the Essex site as well as other expansion locations within the UK. The company has cleared the scaffolding yard location and is investigating on-site power generation and potential acceleration of grid connection processes. The Loughton facility is expected to create 250 permanent jobs once operational. Nscale also noted that the London-wide grid issue does not affect its other contractual commitments. Microsoft declined to comment on the decision. The withdrawal underscores growing challenges in AI data centre development, as delays and infrastructure constraints mount across multiple projects in the sector.
Why This Matters
Microsoft's withdrawal removes a major anchor tenant and £2 billion funding commitment from the UK's largest planned sovereign AI data centre. The project faces a 7–9 year power grid delay (from 2026 to early–mid 2030s), affecting Nscale's IPO timeline and valuation. UK Power Networks' inability to deliver grid capacity illustrates infrastructure constraints that may impact broader AI data centre development across the country and the government's AI competitiveness strategy. Nscale's business model is heavily dependent on two clients (85% of contracted revenue from Microsoft and Anthropic), making this exit material to its financial viability.
Timeline & Sources
Oct 18, 2026
WireMicrosoft's withdrawal from Loughton project announced