Bildeston B1115 Road Closure Begins for £1 Million Water Infrastructure Upgrade

Anglian Water has begun a £1 million, five-month water infrastructure upgrade on Bildeston's B1115 road, starting June 22, 2026. The project will replace aging pipes that have suffered over 30 bursts in five years, with staged road closures and diversions while maintaining pedestrian and business access.





Quick Facts
Who
Anglian Water
What
Installation of one-kilometre new water pipeline
When
June 22, 2026 (project start)
Where
B1115 High Street, Bildeston, Suffolk
- Installation of one-kilometre new water pipeline
- Road closure in seven stages on B1115 High Street
- Replacement of aging water infrastructure
- Implementation of traffic diversions
- Maintenance of pedestrian access and business operations
Anglian Water has commenced a five-month water infrastructure upgrade project on the B1115 High Street in Bildeston, beginning June 22, 2026. The £1 million scheme involves installing one kilometre of new water pipes across seven phases, with work scheduled for completion by November. The aging pipes have experienced over 30 bursts in the past five years, prompting the infrastructure replacement to reduce future service disruptions and ensure reliable water supply to the village.
The road closure will be implemented in sections to allow construction, with traffic diversions in place for vehicles while pedestrian access and local businesses remain operational. The project begins with traffic lights at the Ipswich Road junction from June 22 to 26, followed by phased closures moving progressively northward through the village. Final phases extend into early 2027, with the last closure scheduled from January 11 to February 26.
Anglian Water emphasized that water and sewer services will not be affected during the works, though advance notice will be provided if any service interruptions become necessary. The authority stressed the importance of the upgrade, noting that the East of England is both the driest region in the country and one of the fastest growing, with 700,000 new residents expected over the next two decades. This project forms part of Anglian Water's broader £427 million investment programme to future-proof the Suffolk water network and meet growing demand.
Why This Matters
This infrastructure upgrade directly impacts residents and businesses in Bildeston by reducing frequent water service disruptions caused by aging pipes that have burst over 30 times in five years. While staged closures will temporarily affect traffic flow on the B1115, the £1 million investment ensures long-term water reliability and supports the region's capacity to serve 700,000 new residents expected over the next 20 years, making this critical maintenance essential for community resilience and growth.
Timeline & Sources
Jun 22, 2026
WireProject begins with Phase 1 traffic lights at Ipswich Road and High Street junction
Jun 26, 2026
WirePhase 1 traffic lights conclude
Jun 29, 2026
WirePhase 2 road closure begins on High Street
Jul 17, 2026
WirePhase 2 road closure ends
Jul 20, 2026
WirePhase 3 road closure begins north of health centre entrance
Jul 31, 2026
WirePhase 3 road closure ends
Aug 3, 2026
WirePhase 4a road closure begins
Aug 14, 2026
WirePhase 4a road closure ends
Aug 17, 2026
WirePhase 4b road closure begins
Aug 28, 2026
WirePhase 4b road closure ends
Aug 31, 2026
WirePhase 4c road closure begins
Sep 4, 2026
WirePhase 4c road closure ends
Sep 7, 2026
WirePhase 5 road closure begins
Sep 29, 2026
WirePhase 5 road closure ends
Sep 30, 2026
WirePhase 6 road closure begins at Wattisham Road
Nov 3, 2026
WirePhase 6 road closure ends
Nov 4, 2026
WirePhase 6 traffic lights begin at Ipswich Road
Nov 6, 2026
WirePhase 6 traffic lights end and main project approaches completion
Jan 11, 2027
WirePhase 7 road closure begins on Bildeston Road
Feb 26, 2027
WirePhase 7 road closure and overall project end